Pickleball Expansion & Parking Lot Project Updates
Staff will provide construction updates throughout the project as they become available.
5/12/25
- Anderson Brothers broke ground on the new parking lot and pickleball courts.
- At their regular meeting, City Council approved adding a 5' strip of asphalt between the existing courts and the new ones. This will allow space for spectating, gear storage, and future lighting needs. This follows the contracter's recommendation to avoid a joint on the playing surface.
5/13/25
- Excavated the parking lot drainage ditch.
- Compacted sub-grade.
5/14/25
- Further built the sub-grade for the courts and parking lot.
- Shaped the parking lot drainage ditch and re-added topsoil.
5/15/25
- Completed sub-grade on the Pickleball courts
5/19/25 - 5/21/25
- Rain Delays
5/23/25
- Finished grade on the Pickleball courts
5/28/25
- Paved Parking Lot
- Paved Connecting Trails
- Paved base lift on the Pickleball Courts
5/30/25
- Paved ware course on the Pickleball Courts
6/4/25 - 6/6/25
- Prepping for seed/fertilizer
6/9/2025
- Erosion control on main drainage ditch
- Elite Fence removed the existing 6' north fence and replaced it with 8' fence. They started driving fence posts.
6/10/2025
- Elite Fence finished driving all posts and started to install chainlink fence.
6/11/2025
- Seeded and fertilized all areas around the parking lot and pickleball courts.
- Fencing completed.
6/30/2025
- Park staff augered holes for the picnic table footings.
7/1/2025
- Park staff poured concrete footings for the picnic tables.
-----------------------------------------------------------------------------------------------------
TENTATIVE SURFACING SCHEDULE (SUBJECT TO CHANGE)
7/7/25 - 7/11/25
7/14/25 - 7/20/25 (the contractor pushed back the schedule due to rain events affecting other projects)